Lead Lined

Specifications - Section 08300/08 34 49
Lead Lined Steel Doors & Frames

Part 1 - General

  1 . 1 Work included Supply only of:
    . 1 Pressed steel frames Lead lined, fire labelled or non-labelled.
    . 2 Hollow metal doors Lead lined, fire labelled or non-labelled.

  1 . 2 Related Work
    . 1 Building frames into walls.
    . 2 Installation of doors and hardware.
    . 3 Drilling and tapping of doors and frames for surface mounted hardware.
    . 4 Caulking of joints between frames and other building components.
    . 5 Finish hardware.
    . 6 Finish painting.
    . 7 Fasteners for frame product in previously placed concrete, masonry or structural steel.
    . 8 Glass and glazing.

  1 . 3 Requirements of Regulatory Agencies
    . 1 Install fire labelled steel door and frame products in accordance with NFPA-80, current edition, except where specified otherwise.

  1 . 4 Warranty
    . 1 Material and workmanship shall be warranted by the manufacturer for a period of five (5) years from the date of supply. Warranty shall apply to replacement or retrofit of product only.

  1 . 5 Approved Manufacturers
    . 1 Ambico Limited
1120 Cummings Avenue
Ottawa, Ontario, Canada,
K1J 7R8
Phone (613) 746-4663
Fax (613) 746-4721
Toll Free Phone (North America): 888 423-2224
Toll Free Fax (North America): 800 465-8561


Part 2 - Products

  2 . 1 Materials
    . 1 Steel: Commercial grade, zinc coated steel to ASTM A653.
    . 2 Door core material to be the following:
A : Honeycomb:Structural small cell (1" max) kraft paper "honeycomb".
B : Lead: Rolled pure sheet lead meeting ASTM B749 current edition. Weight and thickness of lead as required to shield against radiation as determined by specifier.
C : Balance of core materials used in the door core shall be in accordance with manufacturer's proprietary design.
    . 3 Primers: Rust inhibitive touch-up only.

  2 . 2 Fabrication
    . 1 General:
A : Doors and frames shall be swing type with provision for glass where required.
B : Frames and doors shall be blanked, reinforced, drilled and tapped for mortised, templated hardware.
C : Frames and doors shall be reinforced, where required for surface mounted hardware. Drilling and tapping shall be by others, on site, at time of installation.
D : Provide factory-applied, touch-up primer at areas where zinc coating has been removed during fabrication.

  2 . 3 Fabrication - Frames, Welded Type
    . 1 Frame product shall be accurately mitred and securely welded on the inside of the profile.
    . 2 Welded joints shall be ground to a smooth, uniform finish.
    . 3 Floor anchors shall be securely attached to the inside of each jamb profile.
    . 4 Weld in two (2) temporary jamb spreaders per frame to maintain proper alignment during shipment.
    . 5 Glazing stops shall be accurately fitted, butted at corners and fastened to frame sections with counter-sunk, oval head, sheet metal screws.
    . 6 Lead shall be securely attached to inside of frame profile from jamb return to jamb stop on the door side of frame only.

  2 . 4 Fabrication - Doors
    . 1 General
A : Doors shall be swing type, flush, with provision for glass openings as indicated on schedules.
B : Longitudinal edges shall be (mechanically inter-locked) (seamless). Seams shall be (visible) (welded, filled and ground smooth).
C : Top and bottom of doors shall be provided with inverted, recessed, spot welded channels. Exterior doors shall be provided with flush steel top caps.
D : Each face sheet shall be formed from (16)(18) gauge sheet with honeycomb core laminated to door core.
E : Lead shall be securely attached to the inside of the door face.


Part 3 - Execution

  3 . 1 Site Storage and Protection of Materials
    . 1 All materials shall be thoroughly inspected upon receipt and all discrepancies, deficiencies and/or damages shall be immediately reported in writing to the supplier.
    . 2 All materials shall be properly stored on planks or dunnage, out of water and covered to protect them from damage from any cause.

  3 . 2 Installation
    . 1 Set frames plumb, square, level and at correct elevation.
    . 2 Fire labelled frames shall be installed in accordance with NFPA-80, most current edition.
    . 3 Secure anchorages and connections to adjacent construction.
    . 4 Install doors and hardware in accordance with hardware templates and manufacturer's instructions.
    . 5 Install glazing and door silencers in accordance with standard industry procedures.